About our redevelopment
The Cowra Hospital Redevelopment will transform the delivery of healthcare for the Cowra community, delivering high-quality contemporary and accessible care close to home.

The NSW Government has committed $110.2 million to redevelop the Cowra Hospital.

Latest news

16 August 2024 - Ina Drive and Holiday closure

16 August 2024 - Ina Drive and Holiday closure

In order for a series of works to be undertaken in the coming months Ina Drive (between Liverpool Lane and Carleton Street) will be continue to be closed to vehicles until 1 February 2025. View PDF  

Posted 19 Dec 2024
Topping out milestone reached

Topping out milestone reached

The $110.2 million Cowra Hospital Redevelopment has reached a major milestone, with the structure of the building now complete. The 'topping out' of the new hospital is the latest construction milestone for the redevelopment, which will significantly enhance access to healthcare for the Cowra community. More  

Posted 09 Dec 2024
Name the Crane winner announced

Name the Crane winner announced

A local primary school student has officially named the 43m-high tower crane installed to support the
construction of the $110.2 million Cowra Hospital Redevelopment. Mulyan Public School student Locky Gee, was announced winner of the ‘Name the Crane’ competition More  

Posted 18 Nov 2024
Project Update - October 2024

Project Update - October 2024

The hospital’s two-level design is taking shape following progressive concrete pours in recent months. All major
pours are expected to be complete in the coming weeks. View PDF  

Posted 31 Oct 2024

How to build a hospital

  • How to build a hospital

    How to build a hospital

    Hospital planning is a complex process that involved extensive consultation with staff, patients, consumers and the community to ensure the right clinical needs are met.
     

Milestones

  • Dec 2024
    Topping out milestone reached

    Topping out milestone reached

    The $110.2 million Cowra Hospital Redevelopment has reached a major milestone, with the structure of the building now complete. The 'topping out' of the new hospital is the latest construction milestone for the redevelopment, which will significantly enhance access to healthcare for the Cowra community.

  • Aug 2024
    First major concrete pour

    First major concrete pour

    Construction of the $110.2 million Cowra Hospital Redevelopment is moving ahead, with the completion of the first concrete pour for the project.
     

  • Feb 2024
    Construction is underway

    Construction is underway

    A significant milestone for the project was reached today with an official sod turn and smoking ceremony on the site of the new hospital.

  • Oct 2023
    Local Trades Information Session

    Local Trades Information Session

    Local trades are encouraged to attend a drop-in information session on Wednesday 11 October to hear about opportunities to be part of the $110.2 million Cowra Hospital Redevelopment.
     

  • Sep 2023
    Main Works Contract Awarded

    Main Works Contract Awarded

    Work to deliver the $110.2 million Cowra Hospital is another step closer, with the appointment of the main works contractor. Richard Crookes Constructions has been engaged following a competitive tender process 
    to build the redevelopment, which will deliver a sustainable, modern, and purpose-built 
    hospital.

  • Feb 2023
    Early works sod turn

    Early works sod turn

    Enabling work to deliver the new $110.2 million Cowra Hospital has commenced, with the early works contractor appointed for the new state-of-the-art facility. 

  • Dec 2022
    Cowra Hospital Schematic Design

    Cowra Hospital Schematic Design

    The schematic designs for the Cowra Hospital Redevelopment have been unveiled for the new purpose-built health facility for the Cowra community.
     

  • Aug 2022
    Cowra Hospital Concept Design

    Cowra Hospital Concept Design

    The Cowra community has been provided with its first look at designs for the new $110.2 million Cowra Hospital marking a significant milestone for the redevelopment.

  • Jul 2022

    Expressions of Interest for the Aboriginal Working Group

    The Cowra Hospital Redevelopment project team is calling for Expressions of Interest for the Aboriginal Working Group to be involved in the $110.2 million Cowra Hospital project.
     

  • Jun 2022

    Additional funding announced

    In the June 2022-23 State Budget, additional funding of $40 million was announced for the Cowra Hospital redevelopment, bringing the total investment to $110.2 million
     
     

  • Mar 2022
    Cowra Hospital Master Plan

    Cowra Hospital Master Plan

    The Master Plan for the redevelopment of Cowra Hospital was unveiled on 30 March, 2022.

  • Mar 2022
    Masterplanning Information sessions

    Masterplanning Information sessions

    Health Infrastructure invites the local community to find out more about the Cowra Hospital Master Plan at a series of online and face-to-face Drop-in sessions

  • Nov 2021
    Information sessions

    Information sessions

    In October and November 2021, Health Infrastructure invited the local community to participate in online and face-to-face information sessions.

  • Jul 2021
    Team appointed for Cowra Hospital Redevelopment

    Team appointed for Cowra Hospital Redevelopment

    A major step forward for the $70.2 million Cowra Hospital Redevelopment with appointment of the lead consultant team to work with Health Infrastructure.